For this project, we needed to remove a 17-year-old spring tensioner system. It was the first time a project like this was ever attempted.
Project Info:
- Project Title: Wellhead Dampening System Upgrade for Prince platform
- Client Name: Enven
- Completed in March 2017
- Scope of work was to remove a 17 year old spring tensioner system for the walls on the EB1003 TLP Prince.
- We removed the old system and installed a new nitrogen based cylinder system from DTI of Houston.
- This project included numerous hours of fabrication work at our shop as well as removal and installation at the rig location.